Editing Period Values for Assignments
You can enter or edit future period values for assignments of labor, non-labor, and material resource, as well as for role assignments.
- Click Resources.
- On the Resources navigation bar, click Assignments.
- On the Assignments page:
- Click Spreadsheet View.
- For each resource assignment you want to plan, enter or edit the Planned Units and the Remaining Early Units for each time period.
- Click Save.
Tips
- When you modify period values, the curve changes to Manual.
- You can apply a resource curve to an assignment before you edit period values for the assignment. When you apply the resource curve, P6 will spread period values across the planned duration of the activity according to the resource curve distribution. You can then modify the period values as necessary.
Related Topics
Future Period Planning: Troubleshooting
Future Period Planning: Settings
Future Period Planning: Entering and Editing Data
Future Period Planning: Deleting, Copying, Pasting, and Replacing Data
Future Period Planning: Updating Projects
Future Period Planning: Importing and Exporting Data
Future Period Planning: Miscellaneous Information
Last Published Thursday, June 20, 2024