Updating Progress on Steps
Update your steps to record your progress.
To update progress on a step:
- Select an activity.
- On the Activity Details tab of the progress panel:
- Expand the Steps section.
- Select More (Ctrl+Alt+M) to view all steps, if all steps are not visible.
- In the % Complete field, enter a percentage value for your work complete.
- Optionally view and change the values for user defined fields associated with the step.
- If you are finished with the step, either:
- Enter 100 in the percentage field.
- Select Complete Step (Ctrl+Alt+C).
- Select Save (Ctrl+Alt+Enter).
Tips
- Depending on the settings configured by your project manager, your % Complete for the activity may be calculated using steps. Steps either have equal weight or are weighted according to the effort required to complete the step.
- Depending on the settings configured by your project manager, you may be able to see and edit user defined fields.
- You can begin reporting progress on your steps for an activity before you start the activity.
- If you do not see the Steps section, you do not have any steps to complete on this activity and you do not have privileges to add steps to this activity.