Assigning a risk to an activity (P6 Professional Only)
Once a risk has been added, you can assign the risk to an activity to explicitly identify the activity impacted by the risk.
Note: You must have Add/Edit/Delete Risks and Add/Edit Activities Except Relationships privileges to assign or remove risks.
You can assign a risk to an activity while you are adding risks using the Risks view or while managing your activities using the Activities window.
To assign a risk to an activity from the Risks view:
- If you haven't already done so, do the following to display the Risks details:
- Choose Project, Risks.
- Display Risk Details.
- Select the risk to assign to activities.
- Click the Activities tab.
- On the Activities tab, click Assign.
- On the Select Activity dialog box:
- Select the activity you want to assign to the risk.
To assign multiple activities, hold down the Ctrl key, then click each activity to assign.
- Click the Assign icon.
- Select the activity you want to assign to the risk.
To assign a risk to an activity from the Activities window:
- If you haven't already done so, do the following to display the Activity Details:
- Choose Project, Activities.
- Display Activity Details.
- Select the activity to assign to risks.
- Click the Risks tab.
- On the Risks tab, click Assign.
- On the Assign Risks dialog box:
- Select the risk you want to assign to the activity.
To assign multiple risks, hold down the Ctrl key, then click each risk to assign.
- Click the Select icon.
- Select the risk you want to assign to the activity.
Related Topics