Assign the baseline to use for summarization or earned value
To choose which baseline to use for summarizing a project, open the project for which you want to select a project baseline.
- Choose Project, Assign Baselines.
- In the Project field, select the project to which you want to assign a project baseline.
- In the Project Baseline field, select the desired baseline or the current project. If no baseline is designated as active, the current project is used as the baseline project.
Note: You can assign only one project baseline to a project. You must have the appropriate security privileges to select the project baseline.