Check in a project from P6 Pro Local Database
- Log into the EPPM database.
- Open the projects you want to check in.
- Choose File, Check In...
- Select Check in from P6 Pro local database (SQLite) and click Next.
- Enter the Login name and Password for the local database.
- Select the projects to check in and click Next.
- Click Finish.
Note:
- When you check in from a local database, the check in process uses Update Existing rules at the project level. If you do not want to use Update Existing rules, you must use XML check in.
- Existing global data which is used in the project is not updated when you check in a project. New global data which is used in the project is added added to when you check in a project.