Copy and paste cost accounts
- Choose Enterprise, Cost Accounts.
Click the Cost Account ID column label to display the cost accounts hierarchy. An outline symbol in the Cost Account ID column label indicates a hierarchy display. - Select the cost account you want to copy, then click Copy.
- Select the cost account to which you want to add the copy, then click Paste.
Note
- When you copy and paste a cost account, the cost account's activity and project assignments are not copied.