Sort activities
You can specify one or more sorting criteria to control the order of activities in a layout.
- Choose Project, Activities, then choose View, Group and Sort By.
- Click Sort.
- Click Add.
- Click the Field Name column to select the field by which you want to sort.
- Double-click the Sort Order column, then select a sort order: ascending (A to Z or lowest to highest), descending (Z to A or highest to lowest), or hierarchical (this option only appears for fields that are hierarchical).
To sort by additional fields, repeat steps 3 through 5. - Click OK.
- To preview your changes, click Apply.
Note
- If you use both grouping and sorting to organize your layout, the items are grouped first and then sorted.