Activities tab - Update Baseline dialog box
Specify the activities to include:
Choose to update data for all activities or activities that meet a filter's criteria.
All Activities: Overwrites the entire baseline.
Activities within the following filter: Updates filtered activities. Click the browse button to select a filter.
Add new activities and activity data (except actuals): Mark to add new project activities and activity data (except actual units and costs) to the baseline. If you apply a filter, the module will add only new activities that meet the selected filter's criteria.
Delete from baseline any activities no longer in the current project: Mark to delete activities from the baseline that have been removed from the current project. If you apply a filter, this option is not available.
Update existing activities already in the baseline: Mark to update activities in the baseline with activity data that has been modified or added in the current project. If you select this option, click Update Options to select the types of activity and resource/role assignment data to update.