Activity tab of Update Options - Update Baseline dialog box

When updating activity data, include:

Specify the types of activity data you want to update and include the updated baseline.

General activity information: Mark to include general information related to each activity accounted for in the baseline. This data includes the activity name, activity type, duration type, percent complete type, status, calendar, and primary resource.

Relationships: Mark to update and include relationships within a project and with external projects.

Constraints: Mark to include updated constraints and their associated dates.

Dates, duration, and data date: Mark to include Original or Planned  Duration, Remaining Duration, Actual start/finish, Anticipated start/finish, Remaining start/finish, Start/finish, Remaining late start/finish, Suspend/resume dates and Data Date.

WBS assignments: Mark to include activities assigned to a WBS.

Risk assignments (P6 Professional Only): Mark to include risks associated with activities.

Activity UDFs: Mark to include updated UDFs assigned to activities.

Activity code assignments: Mark to include project, global and EPS assignments.

Activity notebooks: Mark to include notebooks assigned to activities.

Steps: Mark to include new steps and changes to previous steps.

Step UDFs: Mark to include updated UDFs assigned to steps.

Expenses: Mark to include existing expenses and to adds new expenses to activities.

Expense UDFs: Mark to include updated expense UDFs.

For activities without resource assignments

Budgeted units and cost: Mark to include planned costs per unit for activities without assigned resources.

Actual units and cost: Mark to include actual costs per unit for activities without assigned resources.