Resource Assignment tab of Update Options - Update Baseline dialog box

When updating resource assignment data, include:

Choose to update existing resource/role assignment data and/or add new resource/role assignments. Choose to update the budgeted or planned and/or actual units and cost for the resource/role assignments.

Update existing resource and role assignments: Mark to update all resource assignment data such as UDF's Resource Codes, cost account, dates, and durations.

The following options are enabled only when a check mark is displayed in the Updating existing resource and role assignments check box.

Budgeted units and cost: Mark to include budgeted or planned units and costs related to existing resource and role assignments.

Actual units and cost: Mark to include actual units and costs related to existing resource and role assignments.

Add new resource and role assignments: Mark to include new resource and role assignments in the baseline.

Budgeted units and cost: Mark to include budgeted or planned units and costs related to new resource and role assignments.

Actual units and cost: Mark to include actual units and costs related to new resource and role assignments.

Activity resource assignment UDFs: Mark to include updated UDFs related to resource assignments for activities.

Activity resource assignment codes: Mark to include updated UDFs related to resource assignments for activities.