Add successor relationships
- Choose Project, Activities.
- Select the activity to which you want to add a successor relationship.
- Display Activity Details, then click the Successors or Relationships tab.
- Click Assign in the Successors tab or in the Successors area of the Relationships tab.
- Assign relationships to activities within the same project and/or assign relationships to activities outside of the current project (external relationships):
To assign relationships within the same project, in the Assign Successors dialog box select the successor activity you want to assign, click the Assign button, then click the Close button.
To assign a relationship to an activity outside of the current project, in the Assign Successors dialog box click the Display Options bar and choose Select Project. Select the external project, then select the successor activity you want to assign. Click the Assign button, then click the Close button. - To specify a successor activity's relationship type, double-click the Relationship Type field, then select a type.
- To specify a successor activity's lag time, double-click the Lag field, then type the lag time value.
- To add comments about a successor activity's relationship, double-click the Comments field, then type your comments.
Tip
- You can add the Successor Details column to the Activity Table to see a list of all successors, the relationship type, and the lag applied to the relationship.
Note
- To display the Relationships tab in Activity Details, click the Layout Options bar, then choose Bottom Layout Options and add the Relationships tab to the Display Tabs column list.
Related Topics
Last Published Friday, October 4, 2024