Assign an issue to a resource

  1. Choose Project, Issues, then select the issue.
  2. Display Issue Details, then click the Details tab.
  3. In the Applies to Resource field, click , select the resource to which you want to assign the issue, then click the Select button.

Note

Related Topics

Assign an issue to an activity

Display window details



Last Published Wednesday, April 10, 2024