Change predecessor relationships
- Choose Project, Activities.
- Select the activity whose predecessor relationship you want to change.
- Display Activity Details, then click the Predecessors or Relationships tab.
To add a predecessor, click Assign in the Predecessors tab or in the Predecessors area of the Relationships tab. Select the predecessor activity you want to add.
To change a relationship type, double-click the appropriate Relationship Type field, then select a new relationship type.
To change a lag time value, double-click the appropriate Lag field, then enter a new time value.
To remove a predecessor, select the predecessor you want to remove, then click Remove.
Related Topics
Last Published Friday, October 4, 2024