Change successor relationships
- Choose Project, Activities.
- Select the activity whose successor relationship you want to change.
- Display Activity Details, then click the Successors or Relationships tab.
- To add a successor, click Assign in the Successor tab or in the Successors area of the Relationships tab. Select the successor activity you want to add.
To change a relationship type, double-click the appropriate Relationship Type field, then select a new relationship type.
To change a lag time value, double-click the appropriate Lag field, then enter a new time value.
To remove a successor, in the Successor Activity column select the successor you want to remove, then click Remove.