- Choose Project, Activities, then select the activity whose constraint you want to define.
- Display Activity Details, then click the Status tab.
- In the Primary field, select a constraint type.
- Click in the Date field, then select the date to which the constraint applies.
- In the Secondary field, select a constraint type (if necessary).
- Click in the Date field, then select the date to which the constraint applies.
Notes
- The Secondary constraint list is filtered based on the value you select in the Primary constraint field.
- You cannot apply constraints to Level of Effort or WBS Summary activity types.
Related Topics