Estimate at Completion

The estimated cost at completion for the activity. Computed as the actual total cost plus the estimate-to-complete cost; Estimate at Completion = Actual Cost + Estimate to Complete. Note that the method for computing Estimate to Complete depends on the earned-value technique selected for the activity's WBS.