Example: Determining Resource Availability
If the selected resource is one person, a reasonable value may be 8 hours (units) per day (duration). In this case, the Max Units/Time would be 8.00h/ d, or 8 hours of work per day. Similarly, if the selected resource is a department with 5 people, then the Max Units/Time may be 40.00h/ d. This means that 5 people can perform 40 hours of work per day, rather than 1 person performing 8 hours of work per day.