Finish milestone activity

A finish milestone activity marks the end of a major stage in the project. Since a finish milestone activity does not have a duration, it is sometimes referred to as a "zero duration activity."

A finish milestone may have a primary resource and expenses associated with it, but cannot have resource assignments, role assignments, or time-based costs such as labor. You can assign work products and documents to a finish milestone.