Remove progress from an activity
- Choose Project, Activities, then select the activity.
- Display Activity Details, then click the Status tab.
- Clear the Started and/or Finished checkboxes.
Notes
- P6 Professional will calculate the durations and remaining units based on the Link Budget and At Completion for Not Started Activities setting in the Project Details, Calculations tab.
- If you remove progress from an activity by clearing the Started checkbox, all past period actual data stored for that activity is deleted (except earned value units and cost and planned value units and cost).
- In the Activities window, you can also display the Activity Status column in which you can edit activity status.
Related Topics