Specify leveling priorities
- Choose Tools, Level Resources.
- In the Leveling Priorities area, click Add.
- Select a new leveling priority.
A priority within the table takes precedence over any priorities below it. - Specify a sort order.
- Click Level.
Notes
- To remove a priority from the list, select the priority, then click Remove.
- To edit a priority, click the field name, then select a new field name and/or double-click the Sort Order column and select Ascending or Descending.
- If multiple projects are open when you level resources, you must select which project's settings to use when leveling.
Related Topics