Setting Overtime Policy
P6 Team Member Setup Tasks > Timesheets Setup Tasks > Timesheets Implementation > Configuring Resources for Timesheets
To set overtime policy, which enables users to enter overtime in their timesheets:
- Click Resources.
- On the Resources navigation bar, click Administration.
- On the Administration page, click the Resources tab.
- On the Resources tab, click the Settings detail window.
- In the Settings detail window, select the Overtime Allowed option.
- In the Overtime Factor field, type the overtime factor by which the resource's standard price is multiplied to determine the overtime price (standard price * overtime factor = overtime price).
Note: In P6 and P6 Team Member, resources can enter overtime using separate overtime fields.
Related Topics
Configuring Resources for Timesheets
Assigning Associated Resources
Configuring Resource Settings for Timesheet Reporting