Updating the Early Warning Register

To update the early warning register:

  1. Navigate to your Contract Shell.
  2. From the left Navigator, select Early Warnings, and then select Early Warning Register.
  3. Select the Early Warning record you want to update.

    The Early Warning Register form is displayed.

  4. Select the Edit button.
  5. Select the Actions tab.
  6. Select Add and complete the required fields in the Actions tab. If required, you can add multiple line item records.
  7. In the Line Item Status drop-down menu, select the proposal status (Open or Closed). The Project Manager can update the proposal status.
  8. In the Status drop-down menu, select the early warning register status.
  9. Select Submit to update the record with your changes.