View the Import Audit Log
- Navigate to:
- (For a Planning Manager at the company level) Go to the Company Workspace tab and switch to User mode. In the left Navigator, select Planning Manager.
- (For a Planning Manager at the project/shell level) Go to the project/shell tab where the Planning Manager resides and switch to User mode. In the left Navigator, select Planning Manager.
The system expands the navigator to show the planning types and their corresponding items and sheets.
- Click the [planning item] - Items node.
- In the [planning item] log, select the applicable item.
- In the Actions menu, click View Import Audit Log.
- In the Import Audit Log view information pertaining to the import process that created the planning item such as the name of the CSV or Microsoft Excel file that was imported, the date that the item was created and completed, the name of the user who performed the import, and so on.
Note: By design, planning items with attachments are not included in the CSV import.
See Also
Access Planning Items and Planning Sheets
Access Planning Items from Master Log - Business Processes node
Planning Manager Item Log (Attributes)
Bulk Edit Planning Items from the Planning Manager Log
Add and Manage Planning Sheet Rows
Add and Manage Planning Sheet Columns
Modify Planning Items from a Planning Sheet
Grant Planning Sheet Permission
Understanding Reverse Auto-population
Last Published Friday, June 6, 2025