Auto-Scheduling
If the user goes to the toolbar, clicks Update, and selects Linked Schedule Sheets, only the Activity Data will get updated on the destination (linked) Schedule Sheets from the template, and not the sheet properties.
- If Auto-scheduling is enabled in the Linked (destination) Schedule Sheet, after the Activity Dates update is processed by clicking Update and selecting Linked Schedule Sheets, the re-scheduling will take place.
- If Auto-scheduling is disabled in the Linked (destination) Schedule Sheet, only the Activity Dates is updated and no re-scheduling occurs. That is to state that the change will be reflected in dependent activities.