Schedule Sheet Integration
Unifier supports out-of-the-box (OOTB) mapping for integration between P6 and Unifier, using Schedule Sheets.
This OOTB mapping is available as part of Project Controls installation as a shell template (T-002). You must create a new shell by copying shell template (T-002) to integrate P6 and Unifier using Schedule Sheets.
To view the data mapping fields in Unifier:
- Go to the Company Workspace tab and switch to Admin mode.
- In the left Navigator, select Templates, select Shells, and then select Projects.
- Open the T-002 (Project #) Owner Project Template (Project Name).
- In the left Navigator, select Schedule Manager, and then select Schedule Sheets.
- In the Schedule Sheets log, open Project Schedule Sheet.
- From the File menu, select Data Mapping.
- In the Data Mappings dialog box, click P6 (to select it), click Modify, and then click the Activity tab.
The column name and XML elements are listed as shown below. You can use the XML elements for integration with P6.
Column | XML Element |
---|---|
Activity Name | Name |
Activity Percent | PercentComplete |
Actual Finish Date | ActualFinishDate |
Actual Start Date | ActualStartDate |
Duration | PlannedDuration |
Early Start date | EarlyStartDate |
Early finish date | EarlyFinishDate |
Finish date | PlannedFinishDate |
Late Start date | LateStartDate |
Late finish date | LateFinishDate |
P6 Activity Number | Id |
P6 CBS | CBSCode |
Start date | PlannedStartDate |