Schedule Sheet Integration

Unifier supports out-of-the-box (OOTB) mapping for integration between P6 and Unifier, using Schedule Sheets.

This OOTB mapping is available as part of Project Controls installation as a shell template (T-002). You must create a new shell by copying shell template (T-002) to integrate P6 and Unifier using Schedule Sheets.

To view the data mapping fields in Unifier:

  1. Go to the Company Workspace tab and switch to Admin mode.
  2. In the left Navigator, select Templates, select Shells, and then select Projects.
  3. Open the T-002 (Project #) Owner Project Template (Project Name).
  4. In the left Navigator, select Schedule Manager, and then select Schedule Sheets.
  5. In the Schedule Sheets log, open Project Schedule Sheet.
  6. From the File menu, select Data Mapping.
  7. In the Data Mappings dialog box, click P6 (to select it), click Modify, and then click the Activity tab.

The column name and XML elements are listed as shown below. You can use the XML elements for integration with P6.

Column

XML Element

Activity Name

Name

Activity Percent

PercentComplete

Actual Finish Date

ActualFinishDate

Actual Start Date

ActualStartDate

Duration

PlannedDuration

Early Start date

EarlyStartDate

Early finish date

EarlyFinishDate

Finish date

PlannedFinishDate

Late Start date

LateStartDate

Late finish date

LateFinishDate

P6 Activity Number

Id

P6 CBS

CBSCode

Start date

PlannedStartDate



Last Published Wednesday, July 2, 2025