Cash Flow Analysis

Performing cash flow analysis lets you develop an idea about the financial health and liquidity of your business and determine what is available for you to be used for your business needs. You can perform cash flow analysis based on the following information when using Planned costs, Remaining costs, and Actual costs, from the Activity Sheet:

Unifier uses the Cash Flow module to determine the financial health of portfolio of projects, or a single project, or contracts. You can use the Activity Sheet data as a source for the cash flow curves. Furthermore, you can bring the activities, or assigned resources units or costs, into the cash flow to track the Budget, Baseline, Forecast, and Spends estimates and compare them to see the distribution over time.

When you use the Activity Sheet to manage activities and resource assignments from P6, you can track the Baseline, Forecast, and Actual (Spends) estimates in the cash flow by using the Activity Sheet data.

You can manage scheduling in P6, and you can manage costs either in P6 or Unifier (depending on the schedule type).

When you use P6, you bring the activities, resource assignments, and spread data from P6 into the Unifier Activity Sheet, and from the Activity Sheet the costs and units are rolled up to the Cost Sheet, by way of the CBS Code, and into the Earned Value Management module.

You can use an Activity Sheet as a schedule source in:

Cash flow can support Activity Sheet Schedules in the following cash flow curves:

The following is an example for how to create a cash flow based on an Activity Sheet schedule:

  1. Go to the project/shell tab and switch to User mode.
  2. In the left Navigator, select Cost Manager, and then select Cash Flow to open the Cash Flow log.
  3. Click Create to open and select Manual. The New Cash Flow Worksheet log opens.

The New Cash Flow Worksheet log has two panes with the following toolbar options, blocks, and fields:

Toolbar options:

General block:

Time Scale block:

Right pane:

To establish a schedule manually, or use dates from a schedule sheet, or use dates from an Activity Sheet. Depending on your initial selection, the picker field enables you to open a window and specify your selection.

Example

You can select a type of active manual Activity Sheet (custom, import, manual, or profile) or the System Activity Sheet in the Select Activity Sheet window. The inactive manual Activity Sheets will not be displayed in the Select Activity Sheet window. In the Select Activity Sheet window, click Manual to open the curve type window (Baseline window). In the Baseline window, you can enter values for the following fields:

If the manual Activity Sheet does not have a Baseline schedule, only the "Current" schedule option will be made available, in the Project Type drop-down list.

If you select a System Activity Sheet, the date values (From Date) are from the System Activity Sheet attribute form.

The values are from the manual Activity Sheet or the System Activity Sheet.

You have the option of selecting a manual distribution, or a distribution based on a set profile which is displayed in the drop-down.

When finished, click Add to go to the New Cash Flow Worksheet log.

In the New Cash Flow Worksheet log, right pane, click the Curves drop-down field and select a pertinent option, such as Actuals. This will open the select option window (Actuals window). In the Actuals window, select the values for the following fields:

When finished, click Add to go to the New Cash Flow Worksheet log. In the New Cash Flow Worksheet log, right pane, you will see the added curve, in this case Actuals.

Use the Curves drop-down field to select more curves, such as Forecast, and enter values for each curve.

When finished, click Add to go to the New Cash Flow Worksheet log. In the upper-right corner of the New Cash Flow Worksheet log, click Save & Close to create the cash flow.

When the Cash Flow log displays, you can click on a profile (from the left pane) to see the preview of the curve on the right pane.

At this point, for example, you can check the date values in the curve with the values in the manual Activity Sheet (in the left Navigator, select Schedule Manager, and then select Activity Sheet, open the manual Activity Sheet).

You can update your dates from the manual Activity Sheet, within the Activity Sheet sub-node. After changing the dates, click Save, click Actions, and click Update Baseline. When finished, go to the Cash Flow sub-node, find the item, open the item, and click Refresh to see the new dates.

If you select more than one item, or date, you can change the values by using the Bulk Edit option (toolbar option).

You can use the import and export features to update values.



Last Published Wednesday, July 2, 2025