CBS Type Cash Flow Curve
In a CBS type cash flow curve, you can access the units, or cost data, from the Activity Sheet according to the CBS Code at one of the following levels:
- Activity
- Resource
Note: Be aware that when the cost and schedule are brought in from the System Activity Sheet or a manual Activity Sheet and the Project Type is Baseline or Current, the cash flow uses the earliest date across Planned, Actual, or Remaining Cost as the From Date and the latest date as the To Date.