Activity Sheet

The values for the following cost-related units are calculated according to the assignments, as follows:

Planned Cost & Remaining Cost

Planned Cost and Remaining Cost for the assigned resource will be calculated based on the number of the units * the rate per unit.

Planned Cost is calculated as Planned units * price/unit.

If the rate source is an override, the system uses the rate present in the activity sheet that corresponds to that assignment.

The resource rate is derived from the rate based on the effective date between the start and the finish dates.

The exchange rates for that day are applied if the resource/role does not have the same currency as the project.

Remaining Cost

Remaining Cost for the assigned resource will be calculated based on the number of remaining units * price per unit.

If the rate source is an override, the system uses the price/unit for the calculating remaining cost.

Actual Cost

The system calculates the Actual Cost based on the number of actual units * rate per unit.

The rate is based on the Actual Start Date onwards.

The unit rate is based on the effective date which falls on the actual start date.

At Completion Cost

At Completion Cost value is equal to: Actual Cost + Remaining Cost.

All the calculated costs (Planned Cost, Actual Cost, Remaining Cost, and At Completion Cost) will be rolled up to the activity sheet and to the:

The following units will be rolled up from Assignments tab:

Activity % Complete

The system calculates this field as a simple and intuitive formula for Units % Complete of Activities, with labor or non-labor assignments:

Activity % Complete = [Actual Units] / ([Actual Units] + [Remaining Units] )

Earned Value Calculations at the Activity level:

All the earned value calculations will be performed at activity level.