Working with Schedule Sheets
Working with schedule sheets entails, for example:
- Adding or managing rows and columns.
- Tracking activity progress and costs.
- Managing dependencies and constraints.
In the open schedule sheet, you can view activities and columns in the left pane and view the Gantt chart in the right pane. You can move the split screen bar to the left or right as needed. Scroll bars are available on the bottom of the sheet.
For more information about Activity Sheets and Schedule Sheets, see Activity Manager and—if you have access to the Earned Value Manager feature—refer to the Unifier Earned Value Management User Guide.
To open a project/shell schedule sheet:
- Go to the project/shell tab where the schedule sheet resides and switch to User mode.
- In the left Navigator, select Schedule Manager, and then select Schedule Sheets.
The Schedule Sheets log opens.
- The log lists all active schedule sheets. To view all active and inactive sheets, click the View menu and choose All.
- The Refresh icon indicates whether you must refresh a schedule sheet to display the latest data. The refresh icon is not displayed for schedule sheets that are Inactive or are in a view-only project/shell.
- Double-click a schedule sheet in the log to open the sheet.
If the sheet requires a refresh of the data, you will be asked if you want to refresh the sheet. Click OK to refresh the sheet or No to close the sheet without refreshing the data.
- Select the sheet in the log and click Open, or double-click the sheet. The schedule sheet opens.
In This Section
About activity-level editing restrictions
Restrict Access to Activity fields and columns
Use filters in a schedule sheet
Constrain Schedule Sheet Activities
Add general comments (with or without file attachments)
Refreshing Schedule Sheet data
Lock or unlock the schedule sheet structure
Linked tags and Business Process fields
Last Published Wednesday, July 2, 2025