Manually launching business processes

You can launch BPs manually by selecting an activity and choosing Edit, selecting Linked Business Process, and then selecting Start. To manually launch BPs, these conditions must be met:

Manual launch under various conditions:

Auto-control on Schedule Sheet Properties

Auto-update Activity Status on Activity

System Behavior

On/Off

Checked

Manually launched BP is tracked by the system, and actuals will be auto-populated on launch and completion.

On/Off

Unchecked

Scope Management will not keep track of BP completion and auto-population of actual start and finish dates of manually launched BP.