Enabling Daily History Snapshots and Slowly Changing Dimensions

To enable SCDs and daily history snapshots for a P6 project:

  1. Sign in to P6 EPPM.

    http://<host>:<port>/p6/action/login

  2. In P6, click Projects.
  3. On the Projects screen navigation bar, click EPS.
  4. On the EPS page:
    1. Select a project.
    2. From the icon Row Actions menu of the selected project, select Set Project Preferences.
  5. In the Project Preferences pane:
    1. Ensure the project is configured for publication services.
      1. Click the Analytics & Services tab.
      2. Select the Enable Publication option in the Publication section.
    2. Configure the project's History Level setting.
      1. Click the Analytics & Services tab.
      2. From the History Level list, select Activity (Daily), Activity (Weekly) or Activity (Monthly).

        Note: You should still configure the History Interval setting, but it will only apply to Project and WBS-level history metrics.

    3. Click Save and Close.



Last Published Friday, July 5, 2024