Calculating Metrics in the Burn Down Subject Area

To capture daily trending information, complete the following steps each day to calculate the metrics in the Burn Down subject area:

  1. Update the status of activities in the projects you configured in P6 to be included in the Burn Down subject area. For example, update the Actual and Remaining Units and which activities are completed.
  2. Adjust the data date to correspond to the latest status update.
  3. Run the STARETL process.

    Note: The STARETL run must occur within each calendar date to properly capture daily metrics.