Creating Project UDFs for Burn Down Subject Areas

Only P6 EPPM projects can be manually included to take advantage of the Oracle Primavera Burn Down tables and functionality. This section describes how to create and configure the necessary P6 EPPM project level user-defined fields (UDFs) that the STARETL process needs to include project(s) in Burn Down.

To create the project UDFs, complete the following steps:

  1. Sign in to P6 EPPM with a user account that has the privilege to change enterprise data (for example, admin).
  2. From the Administer menu and select Enterprise Data.
  3. On the Enterprise Data page, expand Projects and select Project UDFs.
  4. On the Project UDFs page:
    1. Add a sys_workdown UDF with a data type of Text.
    2. Add a sys_workdown_date UDF with a data type of Start Date.