Configuring P6 Codes for each Data Source

To extract and load a subset of P6 EPPM codes:

  1. Sign in to Primavera Analytics Administration application:

    http://<host>:<port>/p6rdb

  2. In the sidebar, select icon Status.
  3. In the All list, select staretl<id> or a <custom name for data source>.
  4. In the left pane, select icon Codes.
  5. To migrate codes for the selected P6 data source, select any of the following tabs:
    • Project
    • Activity
      • Notes:
      • A maximum of 240 codes is supported for each area (Project, Activity, and Resource).
      • By default, only those codes that have been enabled through the Primavera Analytics Administration application are exposed in the subject areas.
  6. To select codes for migration:
    1. From the Available Codes list, select one or more P6 codes.
    2. Select Move Right.
  7. To deselect codes from being migrated:
    1. From the Enabled Codes list, select one or more P6 codes you want to remove.
    2. Select left-arrow-button Move Left.
  8. Select Save.