If you set the Mapping mode to Phases or Either Phases or Sub-Items, you can specify Defaults settings for Phases Mode.
To specify Defaults settings for Phases Mode:
- On the Defaults tab under Phases Mode, choose among the following Mapping, Publish, and Update options:
- Add phase date references during initial mapping: Choose this option if you want phase date references to be added to the project in MSP.
- Publish deliverables: Choose this option if you want PPM deliverables to be published as milestone tasks in MSP
- Update phases from corresponding summary tasks: Choose this option if you want PPM phase dates and % complete values to be updated during the Update operation.
- Update deliverables from corresponding milestone tasks: Choose this option if you want the due dates and completion dates to be updated during the Update operation
- Click Next.