P6 Project level fields available for update Items and Portfolios

#

P6 field name in dropdown

P6 field name in Power Client

Data Type

1

AddActualToRemaining

Add Actual To Remain

Flag

2

AddedBy

Added By

Text

3

AnnualDiscountRate

4

AnticipatedFinishDate

Anticipated Finish

Date

5

AnticipatedStartDate

Anticipated Start

Date

6

CheckOutDate

Date Checked Out

Date

7

ContainsSummaryData

Contains Summary Data

Flag

8

ContainsSummaryDataOnly

Contains Summarized Data Only

Flag

9

CreateDate

10

CreateUser

11

CurrentBudget

Current Budget

Cost

12

CurrentVariance

Current Variance

Cost

13

DataDate

Data Date

Date

14

DateAdded

Date Added

Date

15

DiscountApplicationPeriod

16

DistributedCurrentBudget

Distributed Current Budget

Cost

17

EarnedValueETCUserValue

18

EarnedValueUserPercent

19

EstimatedWeight

20

FinishDate

Finish

Date

21

FiscalYearStartMonth

22

ForecastFinishDate

Forecast Finish Date

Date

23

ForecastStartDate

Forecast Start Date

Date

24

HasFutureBucketData

25

IndependentETCLaborUnits

Independent ETC Labor Units

Integer

26

IndependentETCTotalCost

Independent ETC Total Cost

Cost

27

LastSummarizedDate

Last Summarized Date

Date

28

LastUpdateDate

29

LastUpdateUser

30

LevelingPriority

Project Leveling Priority

Integer

31

MustFinishByDate

Must Finish By

Date

32

Name

Project Name

Text

33

OBSName

Resposinble Manager

Text

34

OriginalBudget

Original Budget

Cost

35

OverallProjectScore

36

PlannedStartDate

Planned Start

Date

37

ProjectForecastStartDate

Project Forecast Start

Date

38

ProposedBudget

Proposed Budget

Cost

39

RiskLevel

Risk Level

ValueList

40

ScheduledFinishDate

41

StartDate

Start

Date

42

Status

Project Status

ValueList

43

StrategicPriority

Strategic Priority

Special

44

SummaryAccountingVarianceByCost

Accounting Variance

Cost

45

SummaryAccountingVarianceByLaborUnits

Accounting Variance - Labor Units

Integer

46

SummaryActivityCount

Total Activities

ActivitesRelated

47

SummaryActualDuration

Actual Duration

Integer

48

SummaryActualExpenseCost

Actual Expense Cost

Cost

49

SummaryActualFinishDate

Actual Finish

Date

50

SummaryActualLaborCost

Actual Labor Cost

Cost

51

SummaryActualLaborUnits

Actual Labor Units

Integer

52

SummaryActualMaterialCost

Actual Material Cost

Cost

53

SummaryActualNonLaborCost

Actual Nonlabor Cost

Cost

54

SummaryActualNonLaborUnits

Actual Nonlabor Units

Integer

55

SummaryActualStartDate

Actual Start

Date

56

SummaryActualThisPeriodCost

57

SummaryActualThisPeriodLaborCost

Actual This Period Labor Cost

Cost

58

SummaryActualThisPeriodLaborUnits

Actual This Period Labor Units

Integer

59

SummaryActualThisPeriodMaterialCost

Actual This Period Material Cost

Cost

60

SummaryActualThisPeriodNonLaborCost

Actual This Period Nonlabor Cost

Cost

61

SummaryActualThisPeriodNonLaborUnits

Actual This Period Nonlabor Units

Integer

62

SummaryActualTotalCost

Actual Total Cost

Cost

63

SummaryActualValueByCost

64

SummaryActualValueByLaborUnits

65

SummaryAtCompletionDuration

At Completion Duration

Integer

66

SummaryAtCompletionExpenseCost

At Completion Expense Cost

Cost

67

SummaryAtCompletionLaborCost

At Completion Labor Cost

Cost

68

SummaryAtCompletionLaborUnits

At Completion Labor Units

Integer

69

SummaryAtCompletionMaterialCost

At Completion Material Cost

Cost

70

SummaryAtCompletionNonLaborCost

At Completion Nonlabor Cost

Cost

71

SummaryAtCompletionNonLaborUnits

At Completion Nonlabor Units

Integer

72

SummaryAtCompletionTotalCost

At Completion Total Cost

Cost

73

SummaryAtCompletionTotalCostVariance

74

SummaryBaselineCompletedActivityCount

BL Project Completed Activities

ActivitesRelated

75

SummaryBaselineDuration

BL Project Duration

Integer

76

SummaryBaselineExpenseCost

BL Project Expense Cost

Cost

77

SummaryBaselineFinishDate

BL Project Finish

Date

78

SummaryBaselineInProgressActivityCount

BL Project In-Progress Activities

ActivitesRelated

79

SummaryBaselineLaborCost

BL Project Labor Cost

Cost

80

SummaryBaselineLaborUnits

BL Project Labor Units

Integer

81

SummaryBaselineMaterialCost

BL Project Material Cost

Cost

82

SummaryBaselineNonLaborCost

BL Project Nonlabor Cost

Cost

83

SummaryBaselineNonLaborUnits

BL Project Nonlabor Units

Integer

84

SummaryBaselineNotStartedActivityCount

BL Project Not-Started Activities

ActivitesRelated

85

SummaryBaselineStartDate

BL Project Start

Date

86

SummaryBaselineTotalCost

BL Project Total Cost

Cost

87

SummaryBudgetAtCompletionByCost

Budget At Completion

Cost

88

SummaryBudgetAtCompletionByLaborUnits

Budget At Completion (BAC) - Labor Units

Integer

89

SummaryCompletedActivityCount

Actual Completed Activities

ActivitesRelated

90

SummaryCostPercentComplete

Cost % Complete

PercentComplete

91

SummaryCostPercentOfPlanned

Cost % Of Planned

PercentComplete

92

SummaryCostPerformanceIndexByCost

Cost Performance Index

Unkown

93

SummaryCostPerformanceIndexByLaborUnits

Cost Performance Index - Labor Units

Unkown

94

SummaryCostVarianceByCost

Cost Variance

Cost

95

SummaryCostVarianceByLaborUnits

Cost Variance - Labor Units

Integer

96

SummaryCostVarianceIndex

97

SummaryCostVarianceIndexByCost

Cost Variance Index

Unkown

98

SummaryCostVarianceIndexByLaborUnits

Cost Variance Index - Labor Units

Unkown

99

SummaryDurationPercentComplete

100

SummaryDurationPercentOfPlanned

Duration % Of Planned

PercentComplete

101

SummaryDurationVariance

102

SummaryEarnedValueByCost

Earned Value Cost

Cost

103

SummaryEarnedValueByLaborUnits

Earned Value - Labor Units

Integer

104

SummaryEstimateAtCompletionByCost

Estimate At Completion Cost

Cost

105

SummaryEstimateAtCompletionByLaborUnits

Estimate At Completion - Labor Units

Integer

106

SummaryEstimateAtCompletionHighPercentByLaborUnits

107

SummaryEstimateAtCompletionLowPercentByLaborUnits

108

SummaryEstimateToCompleteByCost

Estimate To Complete

Cost

109

SummaryEstimateToCompleteByLaborUnits

Estimate To Complete - Labor Units

Integer

110

SummaryExpenseCostPercentComplete

Expense Cost % Complete

PercentComplete

111

SummaryExpenseCostVariance

Variance - BL Project Expense Cost

Cost

112

SummaryFinishDateVariance

113

SummaryInProgressActivityCount

Actual In-Progress Activities

ActivitesRelated

114

SummaryLaborCostPercentComplete

Labor Cost % Complete

PercentComplete

115

SummaryLaborCostVariance

Variance - BL Project Labor Cost

Cost

116

SummaryLaborUnitsPercentComplete

Labor Units % Complete

PercentComplete

117

SummaryLaborUnitsVariance

Variance - BL Project Labor Units

Integer

118

SummaryMaterialCostPercentComplete

Material Cost % Complete

PercentComplete

119

SummaryMaterialCostVariance

Variance - BL Project Material Cost

Cost

120

SummaryNonLaborCostPercentComplete

Nonlabor Cost % Complete

PercentComplete

121

SummaryNonLaborCostVariance

Variance - BL Project Nonlabor Cost

Cost

122

SummaryNonLaborUnitsPercentComplete

Nonlabor Units % Complete

PercentComplete

123

SummaryNonLaborUnitsVariance

Variance - BL Project Nonlabor Units

Integer

124

SummaryNotStartedActivityCount

Actual Not-Started Activities

ActivitesRelated

125

SummaryPerformancePercentCompleteByCost

126

SummaryPerformancePercentCompleteByLaborUnits

127

SummaryPlannedValueByCost

128

SummaryPlannedValueByLaborUnits

129

SummaryProgressFinishDate

130

SummaryRemainingDuration

Remaining Duration

Integer

131

SummaryRemainingExpenseCost

Remaining Expense Cost

Cost

132

SummaryRemainingFinishDate

133

SummaryRemainingLaborCost

Remaining Labor Cost

Cost

134

SummaryRemainingLaborUnits

Remaining Labor Units

Integer

135

SummaryRemainingMaterialCost

Remaining Material Cost

Cost

136

SummaryRemainingNonLaborCost

Remaining Nonlabor Cost

Cost

137

SummaryRemainingNonLaborUnits

Remaining Nonlabor Units

Integer

138

SummaryRemainingStartDate

139

SummaryRemainingTotalCost

Remaining Total Cost

Cost

140

SummarySchedulePercentComplete

141

SummarySchedulePercentCompleteByLaborUnits

142

SummarySchedulePerformanceIndexByCost

143

SummarySchedulePerformanceIndexByLaborUnits

144

SummaryScheduleVarianceByCost

Schedule Variance

Cost

145

SummaryScheduleVarianceByLaborUnits

Schedule Variance - Labor Units

Integer

146

SummaryScheduleVarianceIndex

147

SummaryScheduleVarianceIndexByCost

148

SummaryScheduleVarianceIndexByLaborUnits

149

SummaryStartDateVariance

150

SummaryToCompletePerformanceIndexByCost

To Complete Performance Index

Unkown

151

SummaryTotalCostVariance

152

SummaryTotalFloat

153

SummaryUnitsPercentComplete

154

SummaryVarianceAtCompletionByLaborUnits

Variance At Completion - Labor Units

Integer

155

TotalBenefitPlan

Total Benefit Plan

Cost

156

TotalBenefitPlanTally

Total Benefit Plan Tally

Cost

157

TotalFunding

Total Funding

Cost

158

TotalSpendingPlan

Total Spending Plan

Cost

159

TotalSpendingPlanTally

Total Spending Plan Tally

Cost

160

UnallocatedBudget

Unallocated Budget

Cost

161

UndistributedCurrentVariance

Undistributed Current Variance

Cost

162

WebSiteRootDirectory

Web Site Root Directory

Text

163

WebSiteURL

Project Web Site URL

Text



Legal Notices | Your Privacy Rights