4.1 Prerequisite Procedures Overview

Table 4-1 Prerequisite Procedures Overview

Procedure Elapsed Time (hr:min) Procedure Title
  This Step Cum.
Check Required Materials 0:10-0:30 0:10-0:30
DSR ISO Administration 0:15-0:30 0:25-1:00
Verification of Configuration Data 0:20-0:30 0:55-1:30
Data Collection for Source Release 8.0 and Later 0:15-0:20 1:10-1:50
Back Up TKLCConfigData Files 0:15-0:30 1:30-3:05
Full Backup of DB Run Environment at Each Server 0:10-2:00 1:40-5:05

ISO transfers to the target systems may require a significant amount of time depending on the number of systems and the speed of the network. These factors may significantly affect total time needed and may require the scheduling of multiple maintenance windows to complete the entire upgrade procedure. The ISO transfers to the target systems should be performed prior to and outside of the scheduled maintenance window. Schedule the required maintenance windows accordingly before proceeding.