Viewing Forecast to Complete Information

This topic discusses how to view forecast to complete information and personalize the Forecast to Complete pagelet.

Page Name

Definition Name

Usage

Forecast to Complete Pagelet

PC_PE_ETC_VARIANCE

View the forecast to complete date variance for a maximum of five projects with the greatest variance.

Personalize Forecast to Complete Page

PC_PE_ETC_PRS

Define default display information for the Forecast to Complete pagelet.

Use the Forecast to Complete pagelet (PC_PE_ETC_VARIANCE) to view the forecast to complete date variance for a maximum of five projects with the greatest variance.

Navigation:

Click the Personalize Content link on the PeopleSoft Home page.

Select Forecast to Complete.

The pagelet displays a bar graph of a maximum of five projects with the greatest variance. Click the Show All / Enhanced link to access the Forecast to Complete Variance page, which contains more details about date and time variance.

Use the Personalize Forecast to Complete page (PC_PE_ETC_PRS) to define default display information for the Forecast to Complete pagelet.

Navigation:

  • Set Up Financials/Supply Chain > Pagelets > Enterprise Service Automation > Portal Pack Defaults > ESA Portal Pack Pagelet Default Administration

    Click the Forecast to Complete Variance link on the ESA Portal Pack Pagelet Default Administration page.

  • Click the Customize Forecast to Complete icon on the Forecast to Complete pagelet.

This example illustrates the fields and controls on the Personalize Forecast to Complete page.

Personalize Forecast to Complete page

Specify parameters to filter the projects that you want to appear on the Forecast to Complete pagelet.