Specifying Activity Constraints

Page Name

Definition Name

Usage

Activity Definitions - General Information Page

PROJ_ACT_DESCR

Create an activity, specify a constraint, and assign the activity to a project. See also, Activity Definitions - General Information Page

Use the Activity Definitions - General Information page (PROJ_ACT_DESCR) to create an activity, specify a constraint, and assign the activity to a project.

Navigation:

Program Management > General Information > Define Activity General Info

See Also Activity Definitions - General Information Page. These fields are specific to constraints:

Field or Control

Description

Constraint Type

Select the type of constraint from these options:

  • Blank: Leave the field blank if you do not want to define a constraint for this activity.

  • As Late As Possible: This option is not available for summary activities.

  • As Soon As Possible

  • End No Earlier Than: This option is not available for summary activities.

  • End No Later Than

  • Must End On: This option is not available for summary activities.

  • Must Start On: This option is not available for summary activities.

  • Start No Earlier Than

  • Start No Later Than: This option is not available for summary activities.

Constraint Date

Enter the date for the constraint. This field appears only if you select one of these constraint types:

  • End No Earlier Than

  • End No Later Than

  • Must End On

  • Must Start On

  • Start No Earlier Than

  • Start No Later Than