Changing Production Schedule Statuses

This section discusses how to Change Production Schedule Statuses

Page Name

Definition Name

Usage

Production Schedule Status Page

SF_PRDNSCH_STAT_MA

Change the status of a single production schedule from Entered or Firmed to Released. If you do not release the schedule as you're adding it, you can release it here. Change a production schedule from In Process to a prior status.

You must define at least one production schedule.

Dispatch List Selection Page

RUN_SFS2002

Generate a dispatch list.

Define at least one production ID or production schedule.

Production Selection - Report Page

RUN_SFS2002B

Define additional production criteria for the dispatch list.

Print Production Documents Page

RUN_SFS2003

Print production documents for production IDs with a production document status of Ready to Print, reprint production documents, or print production documents for the specified production IDs regardless of the production document print status.

Dispatch Inquiry - Selection Page

SF_DISP_LIST_SEL

Select all scheduled tasks for a work center by a particular date or range of dates that you'd like to view.

Production schedules must have a production status of either Released or In Process.

Dispatch Inquiry - Results Page

SF_DSP_LIST_GRD

Display the requested dispatch list information.

Use the Production Schedule Status page (SF_PRDNSCH_STAT_MA) to change the status of a single production schedule from Entered or Firmed to Released.

If you do not release the schedule as you're adding it, you can release it here. Change a production schedule from In Process to a prior status.

Navigation:

Production Control > Process Production > Release Production > Change Prdn Schedule Status > Prod Sched Status Change

Production Schedule Detail

When no revision is specified, the system uses either the start or due date (based on the BOM explosion date option on the Manufacturing definition page) of the production for determining the bill of material used for producing the item.

To release production, change the production status from Entered or Firmed to Released. If the change was from Entered when you save this page, the system creates the end item's component list and operation list by copying the item's bill of material and routing. Additionally, the routing operations start and due dates and times are calculated. Also, this change enables you to make manual changes to the output list, if desired. If the change was from Firmed, only the status is updated, and the operation, component, and output lists are unchanged.

If you have reversed an In Process production schedule, you can change it to a prior status such as Entered, Firmed, or Released. If you change the status back to Firmed or Released, no changes to the operation, component, or output lists are made. You can also set the production schedule status back to Entered from Released. In this instance, the system deletes the production schedule's component list and operation list, and manual changes to the output list are no longer allowed. If you set the status to Firmed, the system doesn't delete the component list and operation list, but it updates the status.

You can also set the production schedule's status back to Entered from Firmed or Released. In this instance, the system deletes the production schedule's component list and operation list. In addition, the output list is regenerated and cannot be manually maintained.

When you change the status of a released production schedule, if you are integrating to a third-party MES, PeopleSoft Manufacturing uses the Production Order Update EIP to publish a message to the MES with the transaction information. The MES then subscribes to that message and updates the MES information.