Prerequisites

Before you can create a work order, the following conditions must be met:

  • If selecting a requisition line on the work order, the requisition line status must be Approved or Sourced.

  • The requisition must be filled for automatic work order generation from the sourcing and bid pages.

  • A supplier network must be defined for the business unit.

  • Projects must be defined if Project Costing is installed.

  • Activities must be defined.

  • Service types and services must be defined.

To create the logistical tasks associated with the work order, you should:

  • Define tasks.

  • Define a task group.

  • Associate tasks with the task group.

  • Associate the task group with existing service types.