Entering Distribute Costs to Budget Detail Rows

Page Name

Definition Name

Usage

Installation Options - Project Costing Page

INSTALLATION_PC

Enable users to choose the general ledger business unit and department ID distribution for budget detail rows.

Budget Plan Page

PC_BUD_GENERAL

Create and view all budget plans associated with a project, and initiate the Get Plan feature to populate budget detail rows.

See also, Budget Plan Page.

Distribute Activity Resource Amounts Page

PGM_COST_PCT

Enter general ledger business units, department IDs, and distribution percents for the system to use to distribute resource amounts to budget detail rows.

Budget Detail Page

PC_BUD_DETAIL

View budget detail rows that were created by the Get Plan feature.

Use the Budget Plan page (PC_BUD_GENERAL) to create and view all budget plans associated with a project, and initiate the Get Plan feature to populate budget detail rows.

Navigation:

Project Costing, Budgeting, Budget Plan, Budget Plan

Click the Get Plan button on an active budget plan row to launch the Distribute Costs to Budgets process. This process creates budget detail rows based on activity resource amounts. If the budget plan has a budget type of Cost, the system uses the cost amounts from the Resources by Activity page on the detail budget rows. If the budget plan has a budget type of Revenue, the system uses the bill amounts from the Resources by Activity page on the detail budget rows.

  • If existing budget detail rows do not exist for the selection plan, the Distribute Costs to Budgets process creates new budget detail data.

  • If existing budget detail rows exist for the selected plan, the Distribute Costs to Budgets process appends the cost data to the existing budget data.

The Distribute Costs to Budgets process completes one of these actions:

  • If the Allow Get Plan Distribution by Department installation option is activated, the Distribute Activity Resource Costs page appears.

  • If the Allow Get Plan Distribution by Department installation option is not activated, the system creates budget detail rows for budget calendar periods for the general ledger business unit and department ID from the budget items that are entered on the Resources by Activity page.

See Setting Up Budgets in PeopleSoft Project Costing

Use the Distribute Activity Resource Amounts page (PGM_COST_PCT) to enter general ledger business units, department IDs, and distribution percents for the system to use to distribute resource amounts to budget detail rows.

Navigation:

Click the Get Plan button on the Budget Plan page when the Allow Get Plan Distribution by Department option on the Installation Options - Project Costing is enabled.

This example illustrates the fields and controls on the Distribute Activity Resource Amounts page. You can find definitions for the fields and controls later on this page.

Distribute Activity Resource Amounts page

Field or Control

Description

GL Business Unit (general ledger business unit)

Enter the general ledger business unit to be used on budget detail lines for this project.

Department

Enter the department ID to be used on budget detail lines for this project.

Distribution Percent (%)

Enter the percentage for each general ledger business unit and department combination. The sum of the distribution percents must equal 100 percent.

Note: This page does not appear if the project is associated with a project request or if the Allow Get Plan Distribution by Department check box is not selected on the Installation Options - Project Costing page.