Setting Up Activity-Related Information

To set up activity-related information, use these components:

  • Activity Types (PROJ_ACTIVITY_TYPE).

  • Activity Type Status Path (PC_ACTSTATCTL_PNLG).

  • Quality Types (PROJ_QUALITY_DEFN).

  • Define Standard Activities (FS_ACTIVITY_TBL).

Use the PC_STD_ACT_INTFC component interface to load data into the tables for the FS_ACTIVITY_TBL component.

Page Name

Definition Name

Usage

Activity Types Page

PROJ_ACT_DEFN

Create activity types.

Activity Type Status Path Page

PC_ACT_STATCTL_PNL

Define the status path for activities.

Activity Options - Quality Types Page

PROJ_QUALITY_DEFN

Create and modify quality types.

To access this page, select Set Up Financials/Supply Chain > Product Related > Project Costing > Activity Options > Setup PC Activity Quality Type.

Standard Activities Page

FS_ACTVITY_TBL1

Create and modify standard activities.

Use the Activity Types page (PROJ_ACT_DEFN) to create activity types.

Navigation:

Set Up Financials/Supply Chain > Product Related > Project Costing > Activity Options > Setup PC Activity Types

This example illustrates the fields and controls on the Activity Types page. You can find definitions for the fields and controls later on this page.

Activity Types page

Activity type labels identify and group activities to facilitate analysis and reporting on similar activities across projects.

Field or Control

Description

Status

Select the status that determines the availability of an activity type.

Use Status Path

Select to enforce the predefined progression of statuses for activities of this type.

Use the Activity Type Status Path page (PC_ACT_STATCTL_PNL) to define the status path for activities.

Navigation:

Set Up Financials/Supply Chain > Product Related > Project Costing > Activity Options > PC Activity Type Status Path

You must define status types before you define activity type status paths. Activities use the same status type data that you define at the project level.

The procedure to define activity type status paths is the same as the procedure to define status paths for projects.

See Project Type Status Paths.

Use the Standard Activities page (FS_ACTVITY_TBL1) to create and modify standard activities.

Navigation:

Set Up Financials/Supply Chain > Common Definitions > Activities > Setup Standard Activities

This example illustrates the fields and controls on the Standard Activities page. You can find definitions for the fields and controls later on this page.

Standard Activities page

Use this page to predefine activities that users can assign to projects.

Standard activities are keyed by SetID and based on project type. To enable standard activity functionality, select the Standard Activities check box on the Project Costing Definition page for a project. Using standard activities is optional.

Field or Control

Description

Project Type

Enter a project type to restrict the use of this standard activity to projects that have the selected project type and have Standard Activities selected on the Project Costing Definition page. This field appears if you select Projects in the Used By group box.

Leave this field blank for this standard activity to be available to add to any project that does not have a project type assigned.

Used By

Projects: Select for this activity to be available to add to a project as a standard activity.

Performance Measurement: Not used in PeopleSoft Project Costing.

Services Procurement: Not used in PeopleSoft Project Costing.