Applying Production Control Updates

This topic discusses how to apply production control updates.

Page Name

Definition Name

Usage

Apply Production Updates - Apply Planning Messages Page

SF_PRDN_PLN_REQ

Initiate the Apply Planning Messages COBOL process to process the production control updates that you have approved. This process applies the updates so that PeopleSoft Production Management can act on the suggestions made by PeopleSoft Supply Planning.

Use the Apply Production Updates - Apply Planning Messages page (SF_PRDN_PLN_REQ) to initiate the Apply Planning Messages COBOL process to process the production control updates that you have approved.

This process applies the updates so that PeopleSoft Production Management can act on the suggestions made by PeopleSoft Supply Planning.

Navigation:

Supply Planning > Commit Plan > Production Control > Apply Production Updates

Production Selection

Field or Control

Description

Process Production IDs

Select this check box to apply messages for production IDs.

Process Production Schedules

Select this check box to apply messages for production schedules.

Production Message Options

Field or Control

Description

Convert Planned Production

Select this check box to convert planned production into production IDs and production schedules.

Apply Production Changes

Select this check box to apply production change messages to existing production IDs and production schedules.