The Planning Data Inconsistency Report (PLS3001) enables you to identify items to be planned and validates the items that are currently planned.

This topic provides an overview of the Planning Data Inconsistency report and discusses how to create the Planning Data Inconsistency report.

Page Name

Definition Name

Usage

Inconsistency Report Page

RUN_PLS3000

Create the Planning Data Inconsistency report.

Using the Planning Data Inconsistency report (PLS3001), you can:

  • Verify that the master plan items have only master and material components.

  • Verify that material items have only material components.

Note: If the two preceding conditions are violated, the system does not bring the assembly and component relationship into the optimization tables when you run the Load Planning Instance process.

  • Identify the item and production areas that have no valid routing.

    You cannot place a planned order against an area and item combination.

  • Identify the routings that have no item and production areas.

    The Post Updates process (PL_POST) produces an error message when this condition exists for a planned order.

  • Report routings that have no planning times.

    The system does not bring these routings or their related sourcing options into the optimization tables.

  • Identify items with no associated sourcing templates.

  • Identify missing reference routing items.

    You can identify items for which the system will not bring the reference routing item into the planning instance, based on the selection criteria that you specified for this report.

  • Identify potential sourcing options with yields defined as zero.

    Although you cannot define a yield as 0 in PeopleSoft Supply Planning, you can import a yield defined as 0 from an external system. PeopleSoft Supply Planning treats yields defined as 0 as equal to 100 percent.

Note: When specifying search criteria on the Inconsistency Report page, do not populate a field if you intend to search for all of the possible values of the field.

Use the Inconsistency Report page (RUN_PLS3000) to create the Planning Data Inconsistency report.

Navigation:

Supply Planning > Create Plan > Inconsistency Report

Field or Control

Description

Planning Instance

Select a planning instance ID. If you populate this field, the system populates the other request parameters on this page based on the defaults that are associated with the corresponding planning instance ID.