Updating the Early Warning Register
To update the early warning register:
- Navigate to your Contract Shell.
- From the left Navigator, select Early Warnings, and then select Early Warning Register.
- Select the Early Warning record you want to update.
The Early Warning Register form is displayed.
- Select the Edit button.
- Select the Actions tab.
- Select Add and complete the required fields in the Actions tab. If required, you can add multiple line item records.
- In the Line Item Status drop-down menu, select the proposal status (Open or Closed). The Project Manager can update the proposal status.
- In the Status drop-down menu, select the early warning register status.
- Select Submit to update the record with your changes.