The option to reply to a response time extension is available across multiple business processes. In this topic, we used the example of replying to a response time extension on a programme submission. The same instruction apply to other business processes that have the option for response time extension.

  1. Navigate to your Contract Shell.
  2. From the left Navigator, select Tasks.
  3. Select the response time extension task from your Tasks page. The Response Time Extension form is displayed.
  4. Select Accept to accept the task.
  5. For the Response time extension decision field, choose from one of the following options: Accepted or Not Accepted.
  6. Complete the required fields and select Send to submit the reply.