Forecast Type Cash Flow Curve
In a Forecast type cash flow curve, you can access the following, from the Activity Sheet, per CBS code:
- Planned units or costs
- Remaining units or costs
- At Completion units or costs
Note: Be aware that when the cost and schedule are brought in from the System Activity Sheet or a manual Activity Sheet and the Project Type is Baseline or Current, the cash flow uses the earliest date across Planned, Actual, or Remaining Cost as the From Date and the latest date as the To Date.