Setting a Schedule Sheet as the Master Schedule Sheet
The system allows one master schedule sheet per project/shell. You can mark a schedule sheet in a project/shell and a project/shell template as the Master Schedule sheet.
Caution: Upon saving, Master Schedule designation is permanent and cannot be undone.
You can use the master schedule sheet to:
- Drive project dates, for example start date, finish date, planned completion, revised completion
- Drive activity start and end dates
- Track progress of activities over the lifetime of the project
- Drive scope management
- Post costs to the Cost Manager
- Support Cash Flow and Earned Value analysis
- Interface with the Resource Manager for resource assignments and availability
To mark a sheet as the master schedule sheet:
- Go to the shell tab, and switch to User mode.
- In the left Navigator, select Schedule Manager, and then select Schedule Sheets.
- In the Schedule Sheets log, select the sheet that you want to make a master schedule sheet, and select Properties.
- On the General tab of the Properties window, select the Create as master schedule sheet checkbox.
- When the confirmation message appears, select Yes.