Enable and Disable Schedule Sheet Linking

Before you can link project/shell schedule sheets to a template for updating, you must enable the template for linking.

To enable linking for a schedule sheet template:

  1. Go to the Company Workspace tab, and switch to Admin mode.
  2. In the left Navigator, select Templates, select Shells, select the [shell type], and open the [shell template].
  3. In the left Navigator, select Schedule Manager, and then select Schedule Sheets.
  4. On the Schedule Sheets log, select a Schedule Sheet template.
  5. From the Edit menu, select Sheet Linking, and then select Enable.

To disable linking for a schedule sheet template:

  1. On the Schedule Sheets log, select a Schedule Sheet template.
  2. From the Edit menu, select Sheet Linking, and then select Disable.

Disabling Sheet Linking disconnects all project/shell schedule sheets from the linked template; the schedule sheets can no longer receive updates from the template.